Posted on July 4, 2012 by DrRossH in Landfills and Disposal12 MW Plasma Gasification Facility Completed in France – Waste Mangagement World.
France based CHO-Power – has completed construction work on a 12 MW waste to energy facility in Morcenx that utilises plasma gasification technology.
According to the company plant represents and investment of over 40 million Euros and took 17 months to complete.